An office move is judged on one thing: how long you were unable to work. Everything else follows from that.
The good news is that downtime is mostly determined by planning rather than by the move itself.

Start with the building rules, not the boxes
At both addresses, find out early:
- Permitted moving hours. Many managed buildings restrict moves to evenings or weekends.
- Service lift booking. Usually required, often in writing, sometimes weeks ahead.
- Loading dock access and time limits.
- Certificate of insurance requirements. Plenty of buildings will not let a mover in without one, and it takes time to arrange.
- Security and access passes for out-of-hours work.
This is the part that most often forces a date to change, so establish it before committing to anything.
Move outside working hours if you can
A Friday evening or a weekend move means Monday morning is the first time anyone loses productivity — and often nobody does. It is the single biggest lever on downtime.
Plan the sequence, not just the day
Work backwards from the first hour you need to be operational.
- IT and phones go first, and come back first. Everything else can wait; connectivity cannot.
- Set up the new space before the old one empties, if you have overlap on the leases. Even a few days of overlap changes the job entirely.
- Critical staff first. Whoever must be working on Monday gets their workstation set up first.
- Storage and archive last. It is bulky and nothing depends on it.
IT is the part that goes wrong
- Confirm internet at the new address weeks ahead. A business line can need a technician visit and lead times are real. This is the most common cause of a Monday morning that does not work.
- Photograph every setup before unplugging. Cable runs, port assignments, monitor arrangements.
- Label both ends of every cable.
- Back up everything before anything is disconnected.
- Move servers and network hardware deliberately — and if there is anything you cannot afford to have offline, plan that separately from the furniture.
The floor plan
Have one for the new space before moving day, with desks numbered.
Label every box and item with its destination by number rather than by person's name — people move desks, numbers do not. A crew with a numbered plan places things correctly without asking, which is a large part of why a well-planned office move finishes fast.
Tell people what is happening
- Give staff a clear date, what they pack themselves, and where they sit on day one.
- Update the address everywhere: website, Google Business Profile, invoices, letterhead, suppliers.
- Tell customers before, not after.
- Arrange mail forwarding.
Staff normally pack their own desk into a labelled crate. Shared areas, storage and anything specialist is the mover's job.
Furniture and the awkward items
Desks, conference tables and storage units frequently need taking apart to clear doors and lifts — see disassembly and reassembly. Safes and heavy printers need flagging in advance because they change the equipment required.
Measure the awkward pieces against the route at both ends before the day. Moving heavy furniture covers the principles.
A realistic timeline
- 8 weeks: confirm the new space, check building rules at both ends, get quotes.
- 6 weeks: book the move, order internet and phones at the new address.
- 4 weeks: floor plan finalised, desks numbered, staff briefed.
- 2 weeks: address changes begin, IT inventory and backup plan confirmed.
- 1 week: staff pack personal items, final confirmation with building management and the mover.
- Move: IT first, critical staff first, archive last.
What we do
We handle office and small-business relocations — the planning conversation as much as the day itself. If you have a firm date to be operational, tell us and we will work backwards from it.
We serve Orlando, Winter Park, Maitland, Orange County and the surrounding area.
Call In A Zip Moving on (407) 987-2624 to talk through your timeline. See office movers for what the service covers.